The northbound lanes of Valley View will be open soon and will be used for both directions of traffic while the southbound lanes are completed and the detour road is demolished. photo Tony Aiello

Originally slated to be completed in early 2015, lack of rain provides for an Autumn 2014 complete opening

La Mirada~The Valley View Grade Separation Project continues to make steady progress and is on track to be completed by early September.

With the railroad tracks successfully installed on the new bridge structure crossing over Valley View Avenue, crews have been busy completing excavation work to create the underpass. More than 103,000 cubic yards of dirt have been excavated from the site. The excavated dirt was transported and used as fill material on a separate construction project at the Port of Los Angeles.

Construction of the roadway has begun and will occur in two phases. The first phase will see construction of the northbound lanes. Once that is complete, phase two construction of the southbound lanes will begin. During this time, all traffic will be moved onto the newly built northbound lanes, with two lanes in each direction, and the current temporary detour road will be closed for removal.

See all of our photos from this story on our Flickr feed here.